Aspilsan Energy Lithium-Ion Battery Production Facility
The ASPİLSAN Energy Lithium-Ion Battery Production Facility in Kayseri was developed to strengthen Türkiye's domestic energy storage manufacturing capabilities. With approximately 25,000 m² of enclosed space, this high-technology centre brings lithium-ion cell production, battery assembly, R&D and energy solutions for the defence industry under one roof.
- End Client
- Aspilsan Enerji San. Tic. A.Ş.
- Direct Client
- Dost İnşaat Yönetim A.Ş.
- Location
- Kayseri / Türkiye
- Status
- Completed
- Project Period
- October 2020 – December 2021
- Project Area
- 25 000 m²
- Installed Capacity
- 2 MVA
- Contract Role
- Turnkey Electrical Works Contractor
Arenes’ Role
Project Technical Scope
Medium- and Low-Voltage Systems
Medium-voltage supply, transformer infrastructure, low-voltage main switchboards, power installations and distribution systems were installed to meet the facility's energy needs. All infrastructure was commissioned for reliable, uninterrupted operation.
Specialist Electrical Systems
The process-specific installations include a 460 kVA isolation transformer, UPS systems, critical power supplies, power infrastructure for production equipment, ESD protection and earthing, lightning protection, and specialist audio and video systems. All were installed and commissioned for lithium-ion battery production.
Low-Current Systems
Fire detection and alarm, CCTV, IP telephony, data and communications, television, internet and intranet infrastructure were implemented throughout the facility, with successful BMS and SCADA integration.
Testing and Commissioning
All electrical, specialist electrical and low-current systems underwent comprehensive functional and performance testing, and automation integration was verified. The facility was commissioned and handed over for safe, full-capacity production.