Kumas 31.5 kV Distribution & Transmission Line Project
The KÜMAŞ 31.5 kV Distribution and Power Line project in Sivas connects the company's production facilities and generating infrastructure safely and continuously to the national grid. Led by OYAK Renewable Energy, distribution centres, high-voltage connections and transmission infrastructure are being delivered turnkey by ARENES Elektrik.
- End Client
- KÜMAŞ 31.5 kV Distribution and Power Line Project
- Direct Client
- OYAK YENİLENEBİLİR ENERJİ A.Ş.
- Location
- Sivas
- Status
- In Progress
- Project Period
- 2025 - 2026
- Installed Capacity
- 37.5 MVA
- Contract Role
- Turnkey Substation, Switchyard and Power Line Contractor
Arenes’ Role
Project Technical Scope
Medium- and Low-Voltage Systems
31.5 kV distribution infrastructure is being installed, including prefabricated distribution centres, MV switchgear, distribution systems and site connections. Work continues on reliable infrastructure for transmission and distribution needs.
Specialist Electrical Systems
Protection systems, auxiliary services, metering infrastructure and specialist high-voltage electrical installations are being implemented within distribution centres. All electrical infrastructure required for safe, sustainable operation is being integrated.
Low-Current Systems
Data communications, fibre-optic networks, remote monitoring and operational communications are being installed in distribution centres and site facilities, with all systems integrated into central control.
Mechanical Systems
Auxiliary mechanical systems, ventilation and site equipment are being installed for prefabricated distribution centres, supporting safe operation of the energy infrastructure.
Automation Systems
Protection, control and remote monitoring systems are being installed for central management of distribution infrastructure. Automation supports every distribution centre to improve operating performance.
Testing and Commissioning
Testing and commissioning of the 31.5 kV prefabricated distribution centres, high-voltage connections and 29 km distribution line are progressing to schedule. Completed systems are tested and commissioned to the relevant authorities' standards.