CCI - Coca Cola Samarkand Factory
CCI's Coca-Cola Samarkand plant is a major investment in Coca-Cola İçecek's growth strategy in Uzbekistan. Built to meet rising regional demand, it combines modern production technology with efficiency-focused infrastructure. Its electrical systems were delivered turnkey with an emphasis on production continuity, energy efficiency and operational safety.
- End Client
- CCI Coca-Cola Samarkand Plant
- Direct Client
- ORA İNŞAAT
- Location
- Samarkand
- Status
- Completed
- Project Period
- 2024
- Project Area
- 30 000 m²
- Installed Capacity
- 7.5 MVA
- Contract Role
- Turnkey Electrical Works Contractor
Arenes’ Role
Project Technical Scope
Medium- and Low-Voltage Systems
The facility's 7.5 MVA supply includes 10 kV medium-voltage systems, LV main switchboards, distribution lines and power installations, commissioned to provide reliable, sustainable power for its high production demand.
Specialist Electrical Systems
Specialist electrical systems were installed for beverage production lines, filling and packaging units, auxiliary operations, technical rooms and process equipment. Integrated infrastructure supports uninterrupted, efficient production.
Low-Current Systems
Data and communications, fire detection and alarm, CCTV, sound, public address and other low-current systems were installed and integrated throughout the facility, then commissioned to meet operational safety and continuity objectives.
Testing and Commissioning
All electrical and low-current systems underwent functional testing, integration checks and performance verification. The infrastructure was commissioned to operational requirements and handed over turnkey.