ARENES ENGINEERING GROUP

What are you looking for?

Enter between 2 and 80 characters.

ARENES WORLDWIDE

Explore the world of Arenes

Our offices around the world, engineering capabilities and contact channels.

Arenes

Ermaden 34.6 MVA Solar Power Plant Project

The ERMADEN 34.6 MVA Solar Power Plant in Sivas is a major renewable energy investment for Erdemir Madencilik Sanayi ve Ticaret A.Ş., part of OYAK's Mining and Metallurgy Group. Generation, transmission and grid integration infrastructure is being implemented to high engineering standards, with all site activities carried out by ARENES.

End Client
Ermaden – 34.6 MVA Solar Power Plant
Direct Client
OYAK YENİLENEBİLİR ENERJİ A.Ş.
Location
Sivas
Status
In Progress
Project Period
2025
Project Area
424 000 m²
Installed Capacity
34.6 MVA
Contract Role
Turnkey Substation, Switchyard and Power Line Contractor

Arenes’ Role

ARENES is delivering turnkey solar plant site works, a 7.8 km 154 kV transmission line, a 154 kV 25 MVA switchyard with redundancy, substations, automation and SCADA for the ERMADEN 34.6 MVA Solar Power Plant. Work is progressing successfully.

Project Technical Scope

Medium- and Low-Voltage Systems

Medium- and low-voltage distribution systems are being installed to collect and transmit solar generation safely. Work covers installation and integration of collection centres, site distribution, power cabling and auxiliary power systems.

Specialist Electrical Systems

Photovoltaic panels, inverter infrastructure, DC and AC collection systems and specialist generation infrastructure are being installed and integrated to maximise the plant's energy production efficiency.

Low-Current Systems

Data communications, security, site communications networks and remote monitoring systems are being installed for plant operation and safety, with integration into central control infrastructure.

Mechanical Systems

Panel support structures, equipment and auxiliary mechanical infrastructure are being installed throughout the solar site to international standards, coordinated with the electrical systems.

Automation Systems

SCADA, energy monitoring and remote control systems are being installed. All automation is integrated into central control for real-time generation monitoring, reporting and management.

Testing and Commissioning

Testing and commissioning of the 34.6 MVA solar site, 7.8 km 154 kV transmission line, 154 kV 25 MVA switchyard with redundancy, substations and transmission infrastructure are progressing to schedule. Completed systems undergo performance and integration tests for plant commissioning.