Hektas Orhangazi Agricultural Innovation, Training and Experience Center

Hektaş Orhangazi Agricultural Innovation, Training and Experience Centre in Bursa brings agricultural research, product development, training and practical activities together. One of Türkiye's notable agricultural R&D centres, it uses advanced infrastructure and sustainable systems to create a modern research and learning environment.

End Client
Hektaş Orhangazi Agricultural Innovation, Training and Experience Centre
Direct Client
OYAK İNŞAAT
Location
Bursa
Status
Completed
Project Period
2022-2023
Project Area
41 628 m²
Installed Capacity
3.2 MVA
Contract Role
Turnkey Electrical Works Contractor

Arenes’ Role

We completed turnkey mechanical, electrical and low-current systems for Hektaş Orhangazi Agricultural Innovation, Training and Experience Centre, successfully commissioning this technologically advanced facility.

Project Technical Scope

Medium- and Low-Voltage Systems

Medium- and low-voltage distribution systems were installed for the centre's 3.2 MVA capacity. Substations, distribution panels, power installations and building power infrastructure were commissioned for reliable, uninterrupted distribution throughout the facility.

Specialist Electrical Systems

Mechanical installations and specialist technical infrastructure were installed for research areas, training centres, laboratories, technical rooms and shared spaces. Solutions support energy efficiency, user comfort and operational continuity.

Mechanical and Specialist Systems

Mechanical installations and specialist technical infrastructure were installed for research areas, training centres, laboratories, technical rooms and shared spaces. Solutions support energy efficiency, user comfort and operational continuity.

Low-Current Systems

Fire detection and alarm, data and communications, CCTV, card access, sound, public address and other low-current systems were installed and integrated into central management for safety and operational continuity.

Testing and Commissioning

Mechanical, electrical and low-current systems underwent functional testing, integration verification and performance checks. All infrastructure was commissioned to operational requirements and handed over turnkey.