Mesalas Emirdağ Tire Factory And Social Facilities
This major Turkish industrial investment occupies a 90,000 m² site in Emirdağ, Afyonkarahisar, and aims to begin production in the final quarter of 2024.
- End Client
- MESALAS LASTİK SAN. AŞ.
- Direct Client
- MESALAS LASTİK SAN. AŞ.
- Location
- Afyon
- Status
- Completed
- Project Period
- 2024
- Project Area
- 50 000 m²
- Installed Capacity
- 22 MVA
- Contract Role
- Turnkey Electrical Works Contractor
Arenes’ Role
Project Technical Scope
Medium- and Low-Voltage Systems
The facility's 22 MVA infrastructure includes 36 kV medium-voltage systems, transformer substations, LV main switchboards, distribution lines and power installations. This high-capacity, reliable infrastructure was commissioned to serve the factory and social facilities.
Specialist Electrical Systems
Specialist electrical systems were installed for tyre production lines, process equipment, auxiliary production areas, administrative buildings and social facilities. Integrated infrastructure supports efficient, safe and uninterrupted industrial production.
Low-Current Systems
Data communications, fire detection and alarm, CCTV, sound, public address and other low-current systems were installed, integrated and commissioned throughout the facility to meet security, communications and operational continuity needs.
Testing and Commissioning
All electrical and low-current systems underwent functional testing, integration checks and performance verification. The infrastructure was commissioned to operational requirements and handed over turnkey.