Sütaş Bingöl Integrated Facilities
Arenes Elektrik installed and commissioned turnkey 36 kV medium-voltage, 0.4 kV low-voltage and low-current systems at SÜTAŞ's 3,000,000 m² integrated dairy facility in Bingöl.
- End Client
- OYAK Group
- Direct Client
- Sütaş Bingöl Integrated Facilities
- Location
- Bingöl / Türkiye
- Status
- Completed
- Project Period
- 2020 - 2024
- Project Area
- 3 000 000 m²
- Installed Capacity
- 13 MVA
- Contract Role
- Turnkey Electrical Works Contractor
Arenes’ Role
Project Technical Scope
Medium- and Low-Voltage Systems
The facility's 36 kV medium-voltage and 0.4 kV low-voltage distribution systems were installed. Transformer substations, MV switchgear, LV panels, cabling and power installations were commissioned to the design, providing reliable, uninterrupted power distribution.
Specialist Electrical Systems
Specialist electrical systems were installed for the dairy plant, feed mill, power generation plant and auxiliary operations. Process equipment supplies and operational engineering solutions were integrated to support efficient production.
Low-Current Systems
Data communications, fire detection and alarm, CCTV, sound and public address systems were installed and integrated. All low-current infrastructure was commissioned to meet security, communications and operational continuity requirements.
Testing and Commissioning
All installed electrical and low-current systems were functionally tested, and protection, control and safety scenarios were verified. Systems were commissioned to the required performance criteria and handed over turnkey, ready for operation.