Tamek Food Factory - Salihli
TAMEK GIDA's new plant in the Salihli Organised Industrial Zone, Manisa, is a modern food industry investment with advanced production technology and extensive automation. Electrical infrastructure for production, storage and auxiliary operations was delivered turnkey and commissioned to meet high energy demand and uninterrupted production objectives.
- End Client
- TAMEK GIDA A.Ş.
- Direct Client
- TAMEK GIDA A.Ş.
- Location
- Manisa / Salihli
- Status
- Completed
- Project Period
- 2025
- Project Area
- 25 000 m²
- Installed Capacity
- 10 MVA + 1.6 MVA
- Contract Role
- Turnkey Electrical and Mechanical Works Contractor
Arenes’ Role
Project Technical Scope
Medium- and Low-Voltage Systems
36 kV medium-voltage and 0.4 kV low-voltage distribution systems were installed for 10 MVA + 1.6 MVA capacity. Transformer substations, main switchboards, power cabling and power installations were completed, commissioning the factory's entire distribution infrastructure.
Specialist Electrical Systems
Specialist electrical systems were installed for production lines, process equipment, filling and packaging areas, storage units and auxiliary operations. Integrated power and control infrastructure supports efficient, uninterrupted operation at high production capacity.
Low-Current Systems
Data and communications, fire detection and alarm, CCTV, sound, public address and other low-current systems were installed and integrated throughout the facility, then commissioned to meet operational safety and continuity objectives.
Mechanical Systems
All heating, cooling, ventilation and air-conditioning systems, firefighting, compressed air, wastewater, rainwater and domestic water installations were installed to international standards. Environmental conditions in operating areas, offices, technical rooms and shared spaces were designed for high comfort and energy efficiency.
Testing and Commissioning
All medium-voltage, low-voltage and low-current systems underwent functional testing, performance verification and integration. They were commissioned to operational requirements and handed over turnkey.